- Permit Pause: New York has paused incomplete environmental permits for new data centers at or above 50 megawatts for up to one year.
- Exempt Projects: Already-approved developments and smaller institutional facilities remain outside the pause while regulators write statewide standards.
- Unresolved Reach: Officials have not quantified affected proposals, and Hochul has not signed the legislature’s separate 20-megawatt bill.
- Public Pressure: Gallup found 71% opposed a nearby AI data center, with resource use leading opponents’ concerns.
New York Governor Kathy Hochul has signed an order to halt incomplete environmental permits for new data centers using 50 megawatts or more, a cutoff aimed at facilities that can impose large water demands, for up to one year. The pause leaves already-approved developments outside its scope.
New York put the first statewide pause of its kind into effect immediately. As of May 2026, more than 12 gigawatts of large loads, including power-intensive facilities, were waiting to connect to the state’s grid. Hochul’s office could not immediately identify how many proposed data centers the order would affect.
What the Pause Covers and What Comes Next
New York halted discretionary environmental permits that were not already deemed complete for facilities using 50 megawatts or more. Reported exemptions cover hospitals, universities and smaller systems. Because the order targets permitting rather than construction, incomplete approvals for the largest proposals are restricted, not construction across the industry.
New York’s utility regulator, the Department of Public Service, will use a Generic Environmental Impact Statement, a statewide review for consistent project rules. Officials must turn assessments of water use, air quality and grid effects into standards developers can satisfy. Research published in 2025 estimated that AI systems could consume up to 23 gigawatts by year-end, illustrating the broader power and water burden behind those tests.
Until regulators complete the standards, developers above the cutoff cannot finish affected approvals, while smaller systems continue through the existing process. Completed standards would end the pause; otherwise, the restriction expires after one year. Publishing the standards early can reopen the permit path before the deadline without changing the 50-megawatt boundary.
Hochul framed the pause as a response to household costs and resource pressure:
“As data center development threatens to hike up utility bills, deplete our natural resources, and create uncertainty for New Yorkers, it’s my responsibility to take action and lead.”
Kathy Hochul, Governor of New York
Hochul’s rationale extends beyond projects delayed by the pause. Under her directive, officials would consider requiring data centers to invest in energy infrastructure and creating a framework for host-community benefit negotiations. Her separate planned tax legislation would seek repeal of sales-tax exemptions for large facilities when lawmakers return in 2027.
Environmental standards, community obligations and tax treatment could create distinct approval and cost tests for future facilities. Officials still have not quantified how many projects will face those tests.
The Unsigned Bill and Public Pressure
In June, state lawmakers passed a separate development bill that included host-community benefits. Its provisions use a lower 20-megawatt threshold, include energy-efficiency goals and call for a separate one-year permit pause. Facilities between 20 and 50 megawatts would fall under that broader threshold but remain untouched by the executive order.
Because Hochul had not signed the bill when the order took effect, its provisions were not law and remain distinct from the executive order. New York’s narrower order made the state-level debate an active permitting constraint while leaving smaller and already-approved projects untouched.
New York was the first state to enact such a pause after Maine Governor Janet Mills vetoed a similar moratorium in April.
Gallup surveyed 1,000 U.S. adults in March 2026 about large AI computing facilities and found that 71% opposed having one nearby, including 48% who strongly opposed one.
Among opponents questioned in April, 50% cited excessive resource use; 18% mentioned water and another 18% identified energy use or grid constraints. Such public concern gives officials a political reason to scrutinize local costs and aligns with the water and grid subjects in New York’s statewide review.
Hochul’s decision on the separate bill will determine whether its lower threshold advances. For projects covered by the executive order, New York must complete the statewide standards before incomplete permits can resume, unless the one-year limit arrives first.


